Sir Reuben Taureka Highway Opens

Posted

Prime Minister Peter O'Neill today opened the new section of Magi Highway from 6 Mile to Bautama and renamed it the Sir Reuben Taureka Highway.

This project was awarded in October 2015 to Hebou Constructions Ltd at the cost of K145.65 million plus GST plus 15% contingency; and we delivered the project on time within the 18 months construction period. I am happy to announce that this is yet another project that we delivered within the contract sum without any single variation. Out of the 15% contingency, we spent K4 million to construct water mains for Eda Ranu’s future use.